A.1.1.1. HARGA SATUAN PEKERJAAN PERSIAPAN
A.1.1.1.11. Pembuatan1 m2 Steger/Perancah dari Bambu s.d. Tinggi 6 meter
| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) | 
|---|
| A | TENAGA KERJA |   |   |   |   |   | 
|   | Pekerja | L.01 | OH | 1 |   |   | 
|   | Tukang kayu | L.02 | OH | 2 |   |   | 
|   | Kepala tukang | L.03 | OH | 0,2 |   |   | 
|   | Mandor | L.04 | OH | 0,05 |   |   | 
|   |   |   |   | JUMLAH HARGA TENAGA   KERJA | 
| B | BAHAN |   |   |   |   |   | 
|   | Bambu diameter   6-8/600 cm |   | Batang | 1,25 |   |   | 
|   | Tali ijuk |   | m3 | 0,186 |   |   | 
|   |   |   |   | JUMLAH HARGA BAHAN | 
| C | PERALATAN |   |   |   |   |   | 
|   |   |   |   | JUMLAH HARGA ALAT | 
| D | Jumlah (A+B+C) |   |   |   |   |   | 
| E | Biaya Umum dan   Keuntungan |   |   | 0,1 | xD |   | 
| F | Harga Satuan   Pekerjaan (D+E) |   |   |   |   |   | 
Catatan:
Pembuatan steger/perancah secara sewa dapat menggunakan analisis bidang SDA.
A.1.1.1.15. Pemasangan 1m2 Pagar BRC Galvanis
| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga   (Rp) | 
|---|
| A | TENAGA KERJA |   |   |   |   |   | 
|   | Pekerja | L.01 | OH | 0,042 |   |   | 
|   | Tukang | L.02 | OH | 0,004 |   |   | 
|   | Kepala Tukang | L.03 | OH | 0,002 |   |   | 
|   | Mandor | L.04 | OH | 0,042 |   |   | 
|   |   |   |   | JUMLAH HARGA TENAGA   KERJA |   | 
| B | BAHAN |   |   |   |   |   | 
|   | Kawat jaring |   | Lbr | 0,1434 |   |   | 
|   |   |   |   | JUMLAH HARGA BAHAN |   | 
| C | PERALATAN |   |   |   |   |   | 
|   |   |   |   | JUMLAH HARGA ALAT |   | 
| D | Jumlah (A+B+C) |   |   |   |   |   | 
| E | Biaya Umum dan   Keuntungan |   |   | 0,1 | xD |   | 
| F | Harga Satuan   Pekerjaan (D+E) |   |   |   |   |   | 
A.1.1.1.16. Pemasangan 1 m2 Panel Beton Pracetak 50x50x240 cm untuk Pagar
| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga   (Rp) | 
|---|
| A | TENAGA KERJA |   |   |   |   |   | 
|   | Pekerja | L.01 | OH | 0,375 |   |   | 
|   | Tukang | L.02 | OH | 0,125 |   |   | 
|   | Kepala tukang | L.03 | OH | 0,012 |   |   | 
|   | Mandor | L.04 | OH | 0,019 |   |   | 
|   |   |   |   | JUMLAH HARGA TENAGA   KERJA |   | 
| B | BAHAN |   |   |   |   |   | 
|   | Panel beton pracetak |   | Lbr | 0,986 |   |   | 
|   | Kolom beton pracetak |   | Batang | 0,525 |   |   | 
|   | Semen Portlan |   | Kg | 45 |   |   | 
|   | Pasir Beton |   | m3 | 0,074 |   |   | 
|   | Kerikil |   | m3 | 0,146 |   |   | 
|   |   |   |   | JUMLAH HARGA BAHAN |   | 
| C | PERALATAN |   |   |   |   |   | 
|   |   |   |   | JUMLAH HARGA ALAT |   | 
| D | Jumlah (A+B+C) |   |   |   |   |   | 
| E | Biaya Umum dan   Keuntungan |   |   | 0,1 | xD |   | 
| F | Harga Satuan   Pekerjaan (D+E) |   |   |   |   |   | 
 
Posting Komentar untuk "A.1.1.1. HARGA SATUAN PEKERJAAN PERSIAPAN"